City Projects

Project Updates

 

Water Tower #2 Coating

 
 

7-26 - Water Tower #2, located at the top of Hickory Boulevard in the Farmers Ridge Subdivision, has a capacity of 400,000 gallons and was constructed in 2005. Lightning struck the tower during a severe thunderstorm on August 24, 2018. Soon after, citizens and City Staff discovered “sheets” of the tower’s protective coating that had separated from the tower and fallen to the ground.

The League of Minnesota Cities determined the coating failure was fully covered under the City’s insurance policy. The City sought competitive bids to remove the remainder of the tank coating and apply a new coating. The bid was awarded to Maguire Iron of Sioux Falls, SD. That work will begin immediately, starting with draining the tower. Residents in Farmers Ridge may notice a slight reduction in pressure during this time, but otherwise water supply will be largely unaffected.

Coating removal will be accomplished by sandblasting. A full shroud will encompass the tower during this process. Once complete, Maguire will begin the multi-stage coating process. The tower will display the current City logo as seen on this website.

 
 

2019 Street Project

 
 

6-30 -

  • Two pipe crews on Sunset today & tomorrow.
  • No work planned 7/4-7-7.
  • Should finish underground on Sunset by Mon 7/8.
  • Grading continues on Prairie going west from Hillcrest.  Curb on Hillcrest today. 
  • No word on paving schedules yet.
  • Oakwood was paved last Friday.
 
  6-25 -
  • Oakwood (2018 project) wear course was paved last Friday
  • Pouring new concrete walk on Buffalo & Park today
  • Common Excavation and street base work continue on Prairie & Hillcrest
  • Water & Sanitary mainline complete on Sunset; Service lines next on Sunset following bacteria test on new watermain
 
 

5-31 -  Hentges is working tomorrow (Saturday). Pipe work will continue in the Hillcrest Dr & Prairie Street area for all of next week. Will then move to Sunset Dr. Park Street & Buffalo Street street section is being constructed with sand & aggregate base with concrete curb & gutter to follow.

 
 

5-17- Sewer & water work will continue on W. Prairie & Hillcrest all of next week. Street excavation & construction will be taking place on Buffalo & Park St.  We expect curb & gutter soon, we are unsure on exactly when.Sunset Drive will have minimal activity for the next week. Call with any questions.

 
  Resident notices have been delivered. Tree removal along the west side of Buffalo Street and the south side of Prairie Street (adjacent to the cemetery) will actually begin Saturday, May 4 and last into Monday, May 6. All streets will be milled on Monday. The millings will be left in-place as a driving surface until underground construction makes its way to the various locations. Underground construction will begin in the Buffalo/Park Street area.  
  Thumbnail map of 2019 Street Project  
  Click on map for larger picture.  
 

Project Liaison

Dennis Steel, Senior Engineering Technician

Bolton & Menk, Inc. / Mobile 507-317-4920 / Dennis.Steel@bolton-menk.com

 

 


Aquatic Center Photo Gallery

(Click on photo for larger photo)

City Council Tour Pouring walls and floor Pouring pool floor and walls Lazy River
Pool Floor Pool Roof 2 Pool Stairs Pool Walls

 

Upcoming Events

S M T W T F S
 
 
 
 
 
1
 
2
 
3
 
4
 
5
 
6
 
7
 
8
 
9
 
10
 
11
 
12
 
13
 
14
 
15
 
16
 
17
 
18
 
19
 
20
 
21
 
22
 
23
 
24
 
25
 
26
 
27
 
28
 
29
 
30
 

Quick Links

Project Updates